NSP logoHong Kong Natural Science
Press Limited
  • HOME
  • JOURNALS
  • BOOKS
  • ABOUT
  • GUIDE
SUBMITLoginRegister

NSP logoHong Kong Natural Science
Press Limited
  • 00852-30697751
  • routhpub@163.com

Office Locations

7th Floor, Block B, New Mandarin Plaza,
14 Science Museum Road, Tsim Sha Tsui,
Kowloon, Hong Kong

Useful Links

  • Home
  • Journals
  • Books
  • About

Author Services

  • Article Processing Charges
  • Open Access Policy
  • Copyright Transfer Agreement
  • Author Contribution Statement

About

NSP stands for Hong Kong Natural Science Press. Specializing in academic publishing, we operate under an open access (OA) model and are committed to delivering high-quality academic publishing services to researchers worldwide.

Copyright © 2026 NSP unless otherwise stated
  1. Home
  2. >
  3. Journals
  4. >
  5. 工程技术与管理研究
  6. >
  7. Volume 2 Issue 4, 2026
Article|OPEN ACCESS

地光伏输变电物资新型运输模式及施工现场管理策略研究

DOWNLOAD PDF

龚良

四川能投建工集团水利水电工程有限公司

曾绍全

四川能投建工集团水利水电工程有限公司

Volume
Volume 2 Issue 4, 2026
Link
/journals/2/articles/355
DOI
10.65285/GCJSYGL.V2I4.001
Copyright
Published by NSP.

Abstract

山地光伏输变电工程建设中,物资运输与施工组织面临的现实困难较为突出。铁塔构件分批到货后塔位间相互混杂、成套组立难以保证,大截面电缆陡坡段牵引力控制难度较大且采购长度与实际路径之间常有偏差,大型设备进场道路与吊装场地条件往往准备不足。本文针对上述问题,梳理了当前“重载索道主干运输、轨道滑道末端补给、无人机辅助配送与巡查”的组合运输模式,进而从塔材成套清点与双向核对、电缆路径逐段实测与牵引力监控、进场条件联合确认与吊装预演、作业面每日交底与工序巡查等方面,探讨了若干可供参考的现场管理方法。

Keywords

  • 山地光伏;输变电物资;塔材运输;索道运输;施工现场管理

Preview

VIEW PDF

References

  • [1]李刚,袁强,吴穹,等.四川高海拔山地光伏电站建设总结[J].科技资讯,2019,17(32):30-32.
  • [2]黄国建.新能源电力项目施工过程中的质量控制与管理[J].电力设备管理,2025,(23):199-201.
  • [3]张勇,彭畅,冯泽彬.山地光伏电站项目施工阶段管理优化研究[J].工程建设与设计,2024,(12):204-206.
  • [4]李愿明.货运索道运输塔材组立铁塔的施工技术[J].企业技术开发,2016,35(12):98-99.